The Iti Lane project will repair the storm-damaged coastal protection structure and restore safe pedestrian access to Cooks Beach. The works are intended to stabilise the damaged section of the rock revetment, protect nearby stormwater infrastructure and reduce the risk of further erosion.
The beach access was damaged during Ex-Tropical Cyclone Vaianu in April 2026. Wave run-up travelled over the ramp and scoured material from behind the structure, causing the ramp, stairs and landing to slump. The damage has also exposed parts of the stormwater outlet and undermined the adjoining boundary fence.
What Council intends to do
The existing concrete ramp will not be rebuilt. The ramp provided a pathway for wave run-up to travel behind the coastal structure and contributed to the damage. The replacement will provide stair access only.
Safety and access while work is planned
The damaged Iti Lane access will remain closed and temporary fencing and warning signs will be maintained. Interim protection is proposed around the damaged structure and adjoining fence. Council also intends to improve the alternative beach access approximately 125 metres west of Iti Lane and provide signs directing beach users to it.
What the community can expect
Iti Lane, Mercury Bay View Map
Iti Lane , Mercury Bay
October 2026Maintain site closure, signage and interim protection
November 2026 Complete detailed design and specification. Confirm stormwater works
November-December 2026 Seek contractor pricing and confirm programme
January-February 2027Construction start
March 2027 Construction complete and access reopened