Thames water main upgrades

  • Completion Date03 October 2025
luis-tosta-SVeCm5KF_ho-unsplash.jpg

We're upgrading some of our drinking water pipelines over the next few months to meet current Council standards and ensure a safe, reliable supply for years to come. 

The work will happen at three locations in Thames and will start from mid-June 2025.  

To reduce the impact on nearby homes, businesses, and traffic, we’ll be using directional drilling where possible to reduce noise, dust, and disruption. 

What to expect: 

  • Affected properties will be notified directly before the work begins. 
  • There may be short-term water supply disruptions during the work, but we’ll do our best to keep these to a minimum and let you know ahead of time. 
  • A temporary water supply will be provided when needed. 
  • Timings may shift slightly depending on contractor schedules. 
  • Access to driveways on Pollen Street will be maintained during the work

Planned work locations and dates: 

  • Parawai Road: Now completed. Previous estimated timeline was 23 June – 1 August (estimated 6 weeks) 
  • Pollen Street (between Grey Street and Willoughby Street): Now completed. Previous estimated timeline was 21 July to 22 August
  • Ngāti Maru Highway (Maramarahi Road to Deeble Road): Starting 8 September (estimated 7 weeks). Previous estimated timeline was 18 August – 3 October.

We’ll keep you informed throughout the project and will share more detailed information as each stage begins. 

Parawai Road

Work on Parawai Road will take place from 23 June to 1 August and is expected to take around six weeks. As of 22 July, this work has now been completed. 

Parawai rd water mains.jpg

Pollen street (between Grey Street and Willoughby Street)

This work has now been completed.

Pollen street.jpg

Access will remain open at all times, but some roadside parking along Pollen Street will be needed for equipment and work vehicles.

Ngāti Maru Highway (Maramarahi Road to Deeble Road)

The final stage of work on Ngāti Maru Highway, between Maramarahi Road and Deeble Road, will occur from 8 September and is estimated to take seven weeks.

Ngāti Maru Highway.jpg